Milestones |
Date |
Project Support Environment |
09/27/2011 |
Project Proposal |
09/27/2011 |
Project Plan Document V1.0 |
10/06/2011 |
Requirements Document V1.0 |
10/20/2011 |
Design Document V1.0 |
11/08/2011 |
Test Plan Document V1.0 |
12/13/2011 |
User Manual V1.0 (Skeleton) |
12/13/2011 |
Developer Manual V1.0 (Skeleton) |
12/13/2011 |
Iteration #1 |
12/13/2011 |
Documents Version 1.x Complete |
12/13/2011 |
Iteration #2 |
01/24/2012 |
Documents Version 2.x Complete |
01/24/2012 |
Iteration #3 |
02/14/2012 |
Documents Version 3.x Complete |
02/14/2012 |
Iteration #4 |
03/13/2012 |
Project Plan, Requirements, Design, Test Plan V4.x
Complete |
03/13/2012 |
NTASC Submission |
03/13/2012 |
THR User Acceptance Testing (begins) |
03/16/2012 |
NTASC Conference |
03/31/2012 |
SRS Poster Submission |
04/10/2012 |
TheraTouch System Rollout |
04/17/2012 |
SRS Presentation |
04/20/2012 |
User Manual and Developer Manual V4.x Complete |
04/24/2012 |
Final Presentation |
05/03/2012 |
Final Submission |
05/04/2012 |