WAR
04/30/12 � 05/06/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Final Presentation |
ALL |
Senior Design Final Presentation |
|
3 |
Complete |
Activity Cleanup |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Cleaning up and documenting code,
debugging |
6
6
6
6 |
|
Complete |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting, testing, debugging
Testing, debugging, layout/style |
18
16 |
|
Complete |
Senior Design Final Presentation Prep |
ALL |
FP Run-throughs, setup, prep |
5 |
|
Complete |
Senior Design DVD |
Cristina Cline |
Create DVD with final project |
5 |
|
Complete |
Documentation |
ALL |
Finalize all documentation V. 4 |
10 |
|
Complete |
WAR
04/23/12 � 04/29/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Activity Cleanup |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Cleaning up and documenting code,
debugging |
8
8
8
8 |
9
10
9
8 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting, testing, debugging
Testing, debugging, layout/style |
18
16 |
18
16 |
In Progress |
Surface Data Collection |
ALL |
Create sessions and complete them on
surface to generate result data for TheraLink |
4 |
4 |
In Progress |
Testing |
Cristina Cline |
Testing |
8 |
10 |
In Progress |
Documentation |
Adam Burt
Joey Wilkinson
Jeff Gettel
Andrew Hughes
Scott Boykin |
Design Doc
User Manual
Requirement Doc
Requirement Doc
Developer Guide |
5
8
3
3
4 |
5
10
4
4
4 |
In Progress |
WAR
04/16/12 � 04/22/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
SRS Presentation |
ALL |
Prep work and participated in the SRS |
5 |
5 |
Complete |
THR Rollout |
ALL |
Delivered Surface and TheraTouch
(Freeplay mode) |
3 |
3 |
Complete |
Activity Testing |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Testing, debugging and cleaning up
activities |
8
6
6
6 |
10
8
7
7 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting, Testing, debugging
Testing, debugging |
18
15 |
18
15 |
In Progress |
Surface Data Collection |
ALL |
Create sessions and complete them on
surface to generate result data for TheraLink |
4 |
4 |
In Progress |
Documentation |
Joey Wilkinson |
Activity Manual |
8 |
8 |
Complete |
Framework |
Scott Boykin |
Debugging and updating |
6 |
6 |
Complete |
WAR
04/09/12 � 04/15/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Activity Development |
Adam Burt
Andrew Hughes
Cristina Cline
Scott Boykin |
Tweaking and testing apps
Block Bash, Wipe the table
Bug fixes and maintenance
Bug fixes |
8
6
8
4 |
8
6
8
4 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting, testing, debugging
Reporting, testing, debugging |
18
15 |
18
15 |
In Progress |
Surface Data Collection |
ALL |
Create sessions and complete them on
surface to generate result data for TheraLink |
4 |
4 |
In Progress |
SRS Poster |
Adam Burt
Joey Wilkinson
Cristina Cline |
Revise poster, add content to sections,
screen shots |
5
4
2 |
5
4
2 |
In Progress |
THR Rollout Prep |
ALL |
Continued prep |
5 |
10 |
In Progress |
Testing |
Cristina Cline |
Testing |
8 |
10 |
Complete |
WAR
04/02/12 � 04/08/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Activity Development |
Adam Burt
Andrew Hughes
Scott Boykin |
Updating his activities
Tweaking/cleaning up his apps
Bug fixes |
3
2
2 |
4
3
3 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting, unit testing, webapp
Reporting, layout & styling, testing |
16
6 |
20
10 |
In Progress |
SRS Poster |
Joey Wilkinson
Adam Burt |
SRS Abstract and Poster |
2
5 |
2
4 |
In Progress |
Documentation |
Joey Wilkinson
Adam Burt
Andrew Hughes
Cristina Cline |
User Manual
Updating Design Doc
Code documentation
Code documentation |
2
2
9
3 |
2
3
8
4 |
In Progress |
THR Rollup Prep |
Cristina Cline |
Working on THR Surface |
3 |
3 |
In Progress |
WAR
03/26/12 � 04/01/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
NTASC Conference |
Scott Boykin
Jeff Gettel
Andrew Hughes
Cristina Cline |
Presentation Prep
Presentation Slides
Presentation Prep |
5
2
5
- |
4
4
5
- |
Complete |
Activity Development |
Adam Burt
Andrew Hughes
Scott Boykin |
Activity changes, Metronome
Block Bash/Wipe the Table
Bug fixes |
4
3
3 |
2
5
3 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson
Cristina Cline |
Reporting / Unit Testing / Fixes
Reporting/Finalizing CSS/Testing
Research/environment setup |
12
10
- |
11
4
2 |
In Progress |
SRS Poster |
Joey Wilkinson
Adam Burt |
SRS Abstract and Poster |
2
4 |
2
5.5 |
In Progress |
Documentation |
Joey Wilkinson |
Continue writing sections |
2 |
2 |
In Progress |
Testing |
Cristina Cline |
Testing |
n/a |
1 |
In Progress |
WAR
03/19/12 � 03/25/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue working on framework |
n/a |
15 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Tweaking and testing apps
Bug fixes and maintenance
Block Bash / Wipe the Table
Vending Machine |
12
n/a
n/a
n/a |
12
3
21
15 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting / Testing
CSS / Layout Design / Testing |
n/a
10 |
n/a
25 |
In Progress |
Testing |
Cristina Cline
Scott Boykin |
Testing |
n/a
n/a |
12
8 |
In Progress |
Documentation |
Joey Wilkinson |
User Manual |
5 |
2 |
In Progress |
WAR
03/12/12 � 03/18/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue working on framework |
1 |
n/a |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Graphics Vending Machine
Bubble Pop / Activity clean up
Block Bash
Vending Machine |
12
8
10
12 |
6
n/a
n/a
n/a |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting / Help Page / Testing
Reporting / CSS / Help Page |
15
20 |
n/a
5 |
In Progress |
SRS Poster |
Joey Wilkinson
Adam Burt |
Meeting to discuss / plan for the SRS |
2 |
1 |
In Progress |
Documentation |
Scott Boykin
Joey Wilkinson |
Revising and Editing current Docs
User Manual |
2
5 |
n/a
2 |
In Progress |
WAR
03/05/2012 � 03/11/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue working on framework |
1 |
1 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Updating ATM & visual AirBalloon
Bubble Pop
Block Bash
Vending Machine |
4
6
10
6 |
6
8
10
4 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Reporting / Help Page / Testing
Reporting / CSS |
10
10 |
10
5 |
In Progress |
SRS Poster |
Joey Wilkinson
Adam Burt |
Meeting to discuss / plan for the SRS |
2 |
1 |
In Progress |
Documentation |
Cristina Cline
Scott Boykin
Joey Wilkinson |
Revising and Editing current Docs
Revising and Editing current Docs
User Manual |
3
5
5 |
0
2
1 |
In
Progress |
System Testing |
Cristina Cline |
Testing |
2 |
0 |
In Progress |
WAR
02/27/2012 � 03/04/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue working on framework |
2 |
1 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Debugging & Air Balloon
Bubble Pop & Path Track
Block Bash
What Time Is It |
10
8
10
5 |
14
7
10
6 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Unit Testing, Reporting, Help Icons and
Help Page |
15
15 |
12
8 |
In Progress |
System Testing |
Cristina Cline |
Testing |
4 |
2 |
In Progress |
WAR
02/20/2012 � 02/26/12 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue working on framework |
2 |
2 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline 8
Andrew Hughes
Scott Boykin |
Continue work on individual activities
and new activities that were assigned |
5
25
10
15 |
17
12
8
12 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Continue development, layout
design/styling, and unit testing |
20
20 |
18
20 |
In Progress |
System Testing |
Cristina Cline |
Testing |
4 |
6 |
In Progress |
Design Document |
Adam Burt |
Revising |
5 |
3 |
In Progress |
Requirements Doc |
Andrew Hughes |
Revising |
1 |
2 |
In Progress |
User Manual |
Joey Wilkinson |
Revising |
4 |
2 |
In Progress |
WAR
02/13/2012 � 02/19/2012 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Work on the framework |
n/a |
2 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Continued work on individual activities |
35 |
10
18
10
8 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Continue development, layout
design/styling, and unit testing |
20 |
23
25 |
In Progress |
Test Planning |
Cristina Cline |
Develop test plan |
n/a |
5 |
In Progress |
Design Document |
Adam Burt |
Revising |
5 |
2 |
In Progress |
Layout Design |
Adam Burt |
Continue work on layouts and mockups |
4 |
2 |
In Progress |
WAR
02/06/2012 � 02/12/2012 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue updates for Iteration 2 |
8 |
n/a |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Develop activities for Iteration 2 |
35 |
10
n/a
8
n/a |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Update TheraLink for Iteration 2 and unit testing |
20 |
23
15 |
In Progress |
System Testing |
Cristina Cline |
|
10 |
n/a |
In Progress |
Documentation |
Adam Burt
Jeff Gettel
Joey Wilkinson |
Update all documentation to Iteration 2 |
10 |
2
2
2 |
In Progress |
Layout Design |
Adam Burt |
Continue work on layouts and mockups |
4 |
2 |
In Progress |
WAR
01/30/2012 � 02/05/2012 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue updates for Iteration 2 |
8 |
5 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Develop activities for Iteration 2 |
20 |
40 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Update TheraLink for Iteration 2 |
20 |
20 |
In Progress |
System Testing |
ALL |
|
20 |
0 |
In Progress |
Documentation |
ALL |
Update all documentation to Iteration 2 |
30 |
2 |
In Progress |
Layout Design |
Adam Burt |
Application layouts for surface |
- |
2 |
In Progress |
WAR
01/18/2012 � 01/29/2012 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Continue updates for Iteration 2 |
10 |
6 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Develop activities for Iteration 2 |
20 |
25 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Update TheraLink for Iteration 2 |
15 |
30 |
In Progress |
Activity Prototyping |
Joey Wilkinson |
Created prototypes for proposed
activities for Iteration 3 |
5 |
5 |
Complete |
System Testing |
ALL |
|
5 |
12 |
In Progress |
Documentation |
ALL |
Update all documentation to current
Iteration |
5 |
0 |
In Progress |
WAR
12/14/2011 � 01/17/2012 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Scott Boykin |
Update Framework for Iteration 2 |
20 |
15 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline
Andrew Hughes
Scott Boykin |
Develop activities for Iteration 2 and
resolve issues with Iteration 1 activities |
40 |
65 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Update TheraLink for Iteration 2 |
25 |
30 |
In Progress |
WAR
12/06/2011 � 12/13/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Activity Development |
Adam Burt
Scott Boykin
Cristina Cline |
Finalize activities for Iteration #1 |
5 |
5 |
Complete |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Finalize web application for Iteration
#1 |
6 |
6 |
Complete |
Framework Development |
Scott Boykin |
Finalize framework for Iteration #1 |
5 |
5 |
Complete |
Database |
Jeff Gettel |
Finalize framework for Iteration #1 |
6 |
6 |
Complete |
Documentation
|
ALL |
Finalize all documents to V1.x for
Iteration #1 |
3 |
3 |
Complete |
WAR
11/29/2011 � 12/06/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Test Plan |
Andrew Hughes |
Finalize |
5 |
5 |
Complete |
Activity Development |
Adam Burt
Cristina Cline |
Continue development |
6 |
6 |
In Progress |
Framework Development |
Scott Boykin |
Continue development |
5 |
5 |
In Progress |
Web Application Development |
Jeff Gettel
Joey Wilkinson |
Continue development & layout |
6 |
6 |
In Progress |
Database |
Jeff Gettel |
|
3 |
3 |
Complete |
Meetings |
ALL |
Meeting with Rachel King on Wednesday
Meeting with Dr. Skupian and Dr. Stewart
on Thrusday |
3 |
3 |
Complete |
WAR
11/22/2011 � 11/29/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework Development |
Adam Burt
Scott Boykin
Cristina Cline |
|
4 |
10 |
In Progress |
Test Plan |
Andrew Hughes |
Draft |
4 |
5 |
Complete |
Database Meeting |
Jeff Gettel
Joey Wilkinson
Mason McGlothlin
John Farris |
|
1 |
2 |
Complete |
Activity Brainstorming |
Cristina Cline
Joey Wilkinson |
Research/meeting |
4 |
5 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline |
|
4 |
7 |
In Progress |
Database/Web Application Development |
Jeff Gettel
Joey Wilkinson |
Login, scripts, layout, database |
4 |
5 |
In Progress |
WAR
11/15/2011 � 11/22/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Framework |
Adam Burt
Scott Boykin
Cristina Cline |
Finished what was planned so worked
ahead |
6 |
12 |
Complete |
Test Plan |
Andrew Hughes
Jeff Gettel |
Skeleton |
5 |
4 |
Complete |
User Manual |
Joey Wilkinson |
Skeleton, researching |
3 |
3 |
Complete |
Activity Brainstorming |
Joey Wilkinson
Andrew Hughes
Cristina Cline |
Define basic activities to use in
Iteration #1 with Mandy and John &
research |
3 |
8 |
In Progress |
Activity Development |
Adam Burt
Cristina Cline |
Development & research |
- |
4 |
In Progress |
Web Application Meeting |
Jeff Gettel
Mason McGlothlin
John Farris
Joey Wilkinson |
DB Scripts, prototype, general
discussion |
2 |
4 |
Complete |
Web Application Prototype |
Jeff Gettel |
Initial Draft |
6 |
6 |
Complete |
Client Meeting |
Rachel King
Donnell Payne
Cristina Cline
Mandy Seremet
Nipuna Perera
Joey Wilkinson |
11/16 @ 8 AM:
Discuss activity paper prototypes, and
further refine activity definitions |
1 |
1 |
Complete |
WAR
11/8/2011 � 11/15/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Design Document |
Adam Burt
Scott Boykin
Cristina Cline |
Finalize Design Document, diagrams and
modeling |
20 |
12 |
Complete |
Test Plan |
Andrew Hughes
Jeff Gettel |
Skeleton |
6 |
2 |
In Progress |
Activities Brainstorming |
Joey Wilkinson
Andrew Hughes
Cristina Cline |
Brainstorming |
3 |
3 |
In Progress |
TheraLink |
Cristina Cline |
Prototyping |
5 |
5 |
In Progress |
Tech. Framework Collaboration |
Cristina Cline
Scott Boykin
Adam Burt |
Discuss Framework |
2 |
2 |
Complete |
Schedule |
Joey Wilkinson |
Finalize current version |
2 |
2 |
Complete |
User Manual |
Joey Wilkinson |
Skeleton |
4 |
1 |
In Progress |
Use Cases |
Jeff Gettel
Andrew Hughes
Joey Wilkinson |
Add/Updating use cases |
6 |
6 |
Complete |
Client Meeting |
Rachel King
Donnell Payne
Cristina Cline
Mandy Seremet
John Farris |
11/9 @ 3 PM :
Defining activity. |
2 |
2 |
Complete |
WAR
11/1/2011 � 11/8/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Design Document |
Adam Burt
Scott Boykin
Cristina Cline |
Finalize, diagrams and modeling |
14 |
|
In Progress |
Requirements Document |
Jeff Gettel
Cristina Cline
Andrew Hughes |
Finalize |
8 |
10 |
Complete |
Activities Brainstorming |
Joey Wilkinson
Andrew Hughes
Cristina Cline |
|
3 |
6 |
In Progress |
Project Plan |
Cristina Cline
Joey Wilkinson |
Revising |
3 |
3 |
Complete |
Schedule & Gantt Chart |
Joey Wilkinson |
Schedule and Gantt Chart |
1 |
3 |
In Progress |
Pain Survey |
Joey Wilkinson |
Paper Prototype |
1 |
2 |
Complete |
WAR
10/25/2011 � 11/1/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Design Document |
Adam Burt
Scott Boykin |
Work on Design Document Draft II |
2 |
5 |
Complete |
Brainstorm Activities |
Joey Wilkinson
Andrew Hughes |
Work with Team Hands-On (Mandy and John) |
3 |
3 |
In Progress |
Unite Requirements Document |
Jeff Gettel
Joey Wilkinson
Andrew Hughes |
Meet with Team Hands-On (Kevin, Mason, John) standardize |
3 |
10 |
Complete |
Tech. Framework Collaboration |
Cristina Cline
Scott Boykin
Adam Burt |
Discuss Framework |
2 |
3 |
Complete |
Schedule & Gantt Chart |
Joey Wilkinson |
Update Schedule and Gantt Chart |
1 |
2 |
In Progress |
WAR
10/14/2011 � 10/25/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Tech. Framework Collaboration |
Cristina Cline
Scott Boykin
Adam Burt |
Discuss Framework |
2 |
6 |
Complete |
Use Cases |
Andrew Hughes |
Diagram & Writing out use cases |
2 |
n/a |
In Progress |
Design Document |
Adam Burt
Scott Boykin |
Work on Design Document Draft |
3 |
6 |
Complete |
Project Plan |
Joey Wilkinson |
Modify Schedule (bulleted) |
1 |
1 |
Complete |
Database |
Jeff Gettel
Joey Wilkinson |
Continue investigating database,
Optimize and normalize database |
3 |
8 |
Complete |
Web/Surface Prototypes |
Joey Wilkinson
Cristina Cline |
Develop Paper Prototype and PowerPoint
Prototype (Color) |
4 |
6 |
Complete |
WAR
10/07/2011 � 10/14/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Requirements Document |
Jeff Gettel
Andrew Hughes |
Complete Phase II Draft |
6 |
6 |
Complete |
Client Meeting Questions |
ALL |
Come up with questions to ask in client
meeting on 10/13 |
1 |
1 |
Complete |
Design Document |
Adam Burt
Cristina Cline |
Work on Design Document Draft |
3 |
4 |
In Progress |
Microsoft Surface |
Adam Burt
Scott Boykin |
Continue investigating Microsoft Surface
/ Healing Touches source code |
6 |
9 |
In Progress |
Database |
Jeff Gettel
Joey Wilkinson |
Continue investigating database,
Optimize and normalize database |
5 |
5 |
Complete |
Desktop Application |
Joey Wilkinson |
Develop paper prototype |
3 |
4 |
Complete |
WAR
09/30/2011 � 10/07/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Project Plan Document |
Cristina Cline |
Complete Project Plan |
6 |
7 |
Complete |
Project Plan Document |
Joey Wilkinson |
Append Schedule & Gantt Chart, Other
|
2 |
3 |
Complete |
Desktop Application |
Cristina Cline |
Work on Design and stay involved with DB
and surface programming |
1 |
1 |
Complete |
Design Document |
Adam Burt |
Develop skeleton |
3 |
3 |
Complete |
Microsoft Surface |
Adam Burt |
Consolidating parts into classes for
framework to allow for easier modification later |
8 |
3 |
In Progress |
Microsoft Surface |
Scott Boykin |
Investigate ways to universally launch
any game, Find shared activity features |
6 |
6 |
In Progress |
Website |
Adam Burt
Joey Wilkinson |
Continue adding content, Update WARs,
Schedule, Gantt Chart |
2 |
3 |
Complete |
Database |
Jeff Gettel
Joey Wilkinson |
Continue investigating database,
Optimize and normalize database |
5 |
5 |
In Progress |
Revising Requirements Document |
Jeff Gettel
Andrew Hughes |
Revising to reflect feedback from group
and Dr. Payne |
6 |
8 |
Complete |
WAR
09/23/2011 � 09/30/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Project Proposal |
Cristina Cline |
Completed & Submitted
|
1 |
1 |
Complete |
Project Plan Document |
Cristina Cline |
Formatting & Skeleton |
5 |
4 |
In Progress |
Desktop Application |
Cristina Cline |
Began initial design, desktop app.
solution |
2 |
2 |
In Progress |
Scheduling/WAR/Project (Gantt Chart) |
Joey Wilkinson
|
Updated |
1 |
2 |
Complete |
Microsoft Surface |
Scott Boykin
Adam Burt |
Updating old Framework, Surface code |
10 |
9 |
In Progress |
Website/Logo |
Adam Burt |
Install/Setup |
3 |
3 |
Complete |
Desktop Application |
Cristina Cline |
Updating, Design |
10 |
9.5 |
In Progress |
Requirements Document |
Jeff Gettel
Andrew Hughes |
Formatting, Skeleton, Reviewing Document |
3 |
3 |
In Progress |
Database |
Jeff Gettel |
Investigated database to gain info on
normalizing/optimizing |
5 |
8 |
In Progress |
WAR
09/16/2011 � 09/23/2011 |
|||||
Task/Area |
Assigned |
Key Notes/Comments |
Planned Hours |
Actual Hours |
Status |
Project Support Environment |
ALL |
Install/Setup |
20 |
21 |
Complete |
Website Development |
Adam Burt |
Initial Development |
10 |
8 |
Complete |
Camtasia |
Jeff Gettel |
TortoiseSVN Demo |
5 |
3 |
Complete |
Project Proposal |
Cristina Cline |
Template, adding content |
5 |
4 |
In Progress |
Project Plan Document |
Cristina Cline |
Investigated, duplicated database |
5 |
3 |
In Progress |
Subversion |
Scott Boykin, Cristina Cline, Andrew
Hughes |
Install/Setup |
3 |
3 |
Complete |
Desktop Application |
Cristina Cline |
Review Healing Vision�s source code |
2 |
2 |
In Progress |
Scheduling/WAR/Project (Gantt Chart) |
Joey Wilkinson |
Develop format & system, researching
Project |
5 |
5 |
In Progress |
Microsoft Surface |
Scott Boykin
Adam Burt |
Install/Setup, Reviewing Healing Touch�s
source code |
10 |
12 |
In Progress |